Extending row line from Project Tasks into Gant Chart

Per my title, what are the Steps involved? I have MS Project 2024 Standard.

email address removed for privacy reasons 

1 Reply

  • Hello jksjim

    If you mean to display a separator line between the Gantt bars that matches the lines in the task sheet:

    Menu ribbon > Gantt Chart Format > Format > Gridlines > Gridlines... > Gantt Rows > Type: Line > Color: Light Gray, Darker (25%) > OK

    I hope this helps

    Ignacio