Forum Discussion
jim-project
Aug 23, 2025Tin Contributor
Extending row line from Project Tasks into Gant Chart
Per my title, what are the Steps involved? I have MS Project 2024 Standard. email address removed for privacy reasons
- Sep 22, 2025
Thank you Ignacio,
That worked O.K.
jksjim
Ignacio_Martin
Aug 23, 2025Steel Contributor
Hello jksjim
If you mean to display a separator line between the Gantt bars that matches the lines in the task sheet:
Menu ribbon > Gantt Chart Format > Format > Gridlines > Gridlines... > Gantt Rows > Type: Line > Color: Light Gray, Darker (25%) > OK
I hope this helps
Ignacio
jim-project
Sep 22, 2025Tin Contributor
Thank you Ignacio,
That worked O.K.
jksjim