Excel Reporting : Can't connect to calendars with OData anymore (v2)

Hello everyone,

Some of you may remember my previous thread about the same-ish issue (https://techcommunity.microsoft.com/t5/project/excel-reporting-can-t-connect-to-calendars-with-odata-anymore/m-p/4132119) that ended up being solved by a Project Online patch.

 

But somehow, the issue returned. Not the same cause, since it has nothing to do with authentication this time, but the same symptoms : trying to fetch Calendar Exceptions data from an Excel OData query doesn't work anymore.

 

When trying to get the data, I am getting "Error 400 : Cannot get a CSOM-compatible PJContext for an HTTP request that started outside of CSOM."

 

It seems the issue started this morning on my client's tenant.

Has anyone else experienced the same issue ?

  • I just tried again this morning, and it appears to miraculously work!  Who knows how/why it was fixed and/or when they will break it again...

8 Replies

  • RodFromm's avatar
    RodFromm
    Steel Contributor

    Romain_Brunel - I'm getting the same error when retrieving calendar data from Power Query in Excel, but the same query works in the Power BI service.

    • DanMarkoff's avatar
      DanMarkoff
      Brass Contributor

      Do you have any contacts to try to get this fixed again?

      • RodFromm's avatar
        RodFromm
        Steel Contributor

        No, I opened a ticket with Microsoft and they fixed it.  Can you pull the calendar data if you use Power BI Desktop?