Forum Discussion

fgonzalez515's avatar
fgonzalez515
Copper Contributor
May 25, 2023

DOES NOT SHOW % COMPLETED

HELLO COMMUNITY,

 

I REQUEST HELP WITH THE FOLLOWING.

 

I MADE A BUSINESS TEST GANTT, BUT IN THE SCHEDULE IT SHOWS ME THAT THE PROJECT IS 20% COMPLETE AND HAS A DURATION OF 4 DAYS, BUT IN THE PROJECT SUMMARY IT DOES NOT SHOW ME THIS INFORMATION.

 

HOW CAN I SOLVE THAT?

 

 

 

 

4 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    fgonzales515,
    First of all you do not need to shout (i.e. all caps), it will not get you a quicker or better answer.

    What version of Project are you using? It looks like your second screen shot shows the Gantt Chart view of Project desktop but I don't quite understand what the first screen shot is showing. What view is that?

     

    Did you insert the file into a master and that is what is showing in the first screen shot?

    John

    • fgonzalez515's avatar
      fgonzalez515
      Copper Contributor

      John-project 

       

      I'm using Project Online.

      Both captures correspond to Project Online.
      The first is Projects Portfolio and the second capture is Gantt Diagram.
      I don't know if I understand my query.

      In the Gantt Diagram I have a duration of 4 days and 20% Complete, but in the Project Portfolio it does not show me the same.

      • John-project's avatar
        John-project
        Silver Contributor
        fgonzalez515,
        Thanks for clarifying what version you are using. Unfortunately I don't have expertise with Project Online so I can't be of further assistance. Hopefully one of my colleagues will jump in and offer a suggestion.
        John

Resources