Deleting a user on PWA who is an assignment owner
Good day .
I would like to know if there is a way to delete a user who is an assignment owner in various projects. Is there a way to resolve this quicker?
2 Replies
- Mpafane --
The project manager must open each project in which the user is the Assignment Owner of tasks, change the Assignment Owner value to someone else (such as the team member assigned to each task) for each task, and then save and publish the project. That is the only way to resolve this problem. I hope this helps. - EricStarkerFormer Employee