Forum Discussion
Yann-78
Oct 17, 2022Copper Contributor
Copy paste cost rate table across resources
Hi,
I am trying to copy paste the cost rate table customized for each year across resources. The default cost rate as 1 dimension can be pasted un the grid view but the cost rate varying over time needs to be entered manually for each resource. Any idea?
1 Reply
- John-projectSilver ContributorYann-78,
As you found out it is not possible to use copy/paste to transfer cost rate table information across all resources. It can be done manually or, it can also be done with VBA. If you have only a few resources and only a couple of years data, setting it up manually isn't too difficult. However, if you have several resources with a multi-year cost rate plan, then VBA is the best approach.
John