Forum Discussion
salzan
Jun 25, 2021Copper Contributor
Copy a text field from Task table to a text field in the Resource table for all tasks
I'm trying to get the Resource Usage View to display a text field that was filled on the Task View.
I tried importing the text from Task table into a custom field on the resource table but I got nothing.
I also tried writing a formula but couldn't determine how to qualify the text field with Task table so changes would happen in real time.
Can anyone help me with any method that can copy a text field between tables in MS Project Professional?
Thank you in advance.
- John-projectSilver Contributor
Yes, the following Wiki article will explain what you need to do.
If you need further help, let us know.
John
- salzanCopper ContributorThank you very much John-project, that worked perfectly.
- John-projectSilver ContributorYou're welcome and thanks for the feedback. If I answered your question, please consider marking my response as the answer.
John