Copy a text field from Task table to a text field in the Resource table for all tasks
I'm trying to get the Resource Usage View to display a text field that was filled on the Task View. I tried importing the text from Task table into a custom field on the resource table but I got not...
John-project
Jun 24, 2021Silver Contributor
Yes, the following Wiki article will explain what you need to do.
If you need further help, let us know.
John
- salzanJun 24, 2021Copper ContributorThank you very much John-project, that worked perfectly.
- John-projectJun 25, 2021Silver ContributorYou're welcome and thanks for the feedback. If I answered your question, please consider marking my response as the answer.
John