Connecting Project central files to Planner plans

Hi there,

I want to have users updating tasks in Planner plans, but have when i click the Planner link on the right i get the error below

 

"project was unable to establish a connection with https //graph.microsoft.com"

What do I need to do to connect Planner plans into a project?

 

4 Replies

  • Stuartf --

    This feature does not work with the Microsoft Project desktop application unless it is connected to either a Project Online or Project Server instance. Does that describe your situation? Let us know.
    • Stuartf's avatar
      Stuartf
      Brass Contributor

      Thnaks Dale_HowardMVP Yes i'm using Project Online as well  - https://project.microsoft.com/companyDomain


      Cheers,
      Stuart

      • Stuartf --

        The URL you mentioned indicates you are using Project for the Web and NOT Project Online. So, this means you are not going to be able to use the Link Task to Planner Plan feature in Microsoft Project. Hope this helps.