Forum Discussion
Stuartf
Sep 26, 2024Brass Contributor
Connecting Project central files to Planner plans
Hi there, I want to have users updating tasks in Planner plans, but have when i click the Planner link on the right i get the error below "project was unable to establish a connection with...
Sep 26, 2024
Stuartf --
This feature does not work with the Microsoft Project desktop application unless it is connected to either a Project Online or Project Server instance. Does that describe your situation? Let us know.
This feature does not work with the Microsoft Project desktop application unless it is connected to either a Project Online or Project Server instance. Does that describe your situation? Let us know.
- StuartfOct 02, 2024Brass Contributor
Thnaks Dale_HowardMVP Yes i'm using Project Online as well - https://project.microsoft.com/companyDomain
Cheers,
Stuart- Oct 02, 2024Stuartf --
The URL you mentioned indicates you are using Project for the Web and NOT Project Online. So, this means you are not going to be able to use the Link Task to Planner Plan feature in Microsoft Project. Hope this helps.- agasthyaspJan 16, 2025Copper Contributor
Hi Dale,
I am using Project online in MS Project MSO but still I see the above error. Is this because of any missing permission or any other issue?