change "work" unit in Project online (PWA)

Hi All

I hope someone can help

Is there a way to change the units of "work" on the project online schedule view and project centre view?

Most PMs in my company work in days rather than hours in the desktop file, but when a project gets uploaded it seems to switch in the above views to hours. 

Thanks for your help

Matt 

  • Matthew --

    I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.

2 Replies

  • Matthew --

    I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.
    • Matthew Russell's avatar
      Matthew Russell
      Copper Contributor

      Hi Dale_HowardMVP 

      Thanks for getting back to me.

      That is frustrating, I'll have to do a calculated column in the project centre to convert hours to days and educate the team in using hours moving forward rather than days.

      Thanks again

      Matt 