change "work" unit in Project online (PWA)

Hi All I hope someone can help Is there a way to change the units of "work" on the project online schedule view and project centre view? Most PMs in my company work in days rather than hours in th...
  • Dale_HowardMVP's avatar
    May 04, 2022
    Matthew --

    I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.