Forum Discussion
Matthew Russell
May 04, 2022Copper Contributor
change "work" unit in Project online (PWA)
Hi All I hope someone can help Is there a way to change the units of "work" on the project online schedule view and project centre view? Most PMs in my company work in days rather than hours in th...
- May 04, 2022Matthew --
I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.
May 04, 2022
Matthew --
I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.
I regret to inform you that even though you can display Work in Days in the Microsoft Project application, it is not possible to display Work in Days in either the Project Center page in PWA or in the Schedule PDP. Sorry, but hope this helps.
Matthew Russell
May 04, 2022Copper Contributor
Thanks for getting back to me.
That is frustrating, I'll have to do a calculated column in the project centre to convert hours to days and educate the team in using hours moving forward rather than days.
Thanks again
Matt