Forum Discussion

Ximo's avatar
Ximo
Brass Contributor
Jan 25, 2023
Solved

Change the lookup table for Project Departments or Resource Departments

Hi, after setting the lookup table it is impossible to change it or delete and recreate these custom fields. Also, I cannot change from multiple to single selection in Project Departments.

 

Do I have to start from scratch on another instance to fix this?

 

 

Thank you!

  • Ximo --

    I have some bad news for you, my friend. Once a lookup table has been selected for a custom field, and then the custom field has been created, it is IMPOSSIBLE to choose a different lookup table for that custom field. If you are not too far down the road on creating on your Project Online instance, I would recommend you start with a fresh instance. Sorry for the bad news, but hope this helps.

2 Replies

  • Ximo --

    I have some bad news for you, my friend. Once a lookup table has been selected for a custom field, and then the custom field has been created, it is IMPOSSIBLE to choose a different lookup table for that custom field. If you are not too far down the road on creating on your Project Online instance, I would recommend you start with a fresh instance. Sorry for the bad news, but hope this helps.
    • Ximo's avatar
      Ximo
      Brass Contributor
      Thanks Dale, just checking 😉