Carrying over text formatting/highlighting when inserting sub-projects into master projects

Is it possible to carry over the formatting (bold, highlight/fill colours etc.) I've applied to a 'template project sheet' when I insert it into a master project, without having the 'Link to Project' checkbox ticked? 

 

(Am aware that the formatting also doesn't carry over if the projects are linked, but my use case will only be with unlinked sub-projects). 

  • BlissL,
    Sorry, no. When you create a static master (i.e. insert subprojects with the "link to project" option unchecked), you are creating a new separate file. As such text formatting does not transfer.

    John

1 Reply

  • John-project's avatar
    John-project
    Silver Contributor
    BlissL,
    Sorry, no. When you create a static master (i.e. insert subprojects with the "link to project" option unchecked), you are creating a new separate file. As such text formatting does not transfer.

    John