Can I assign dates of availability to material resources?
I've been watching basically every video I can find on YouTube, but have not found an answer to this:
Say I have a task: "Dig Hole"
And for that task, I have a material resource: "Shovel"
However, that resource (shovel in this case) is not available before a certain date. Let's say the shovel will not become available for use until 1/1/2024. Therefore, the work cannot start before or until 1/1/2024, when that material resource becomes available.
Is there a way to assign this availability to this material resource, and so then when I have a task and allocate this resource to it, Project can automatically update the Begin Task dates to coincide with when the material becomes available?
1 Reply
- kayakfisherman50 --
Your mistake is assuming that the Shovel resource is a Material resource. The Shovel resource needs to be a Work resource because the shovel actually does "work" in the project. And when you make the Shovel resource a Work resource, you can view and analyze resource availability for this resource, which you CANNOT do if you make the Shovel a Material resource. Hope this helps.