Forum Discussion
kayakfisherman50
Dec 12, 2023Copper Contributor
Can I assign dates of availability to material resources?
I've been watching basically every video I can find on YouTube, but have not found an answer to this: Say I have a task: "Dig Hole" And for that task, I have a material resource: "Shovel" ...
Dec 12, 2023
kayakfisherman50 --
Your mistake is assuming that the Shovel resource is a Material resource. The Shovel resource needs to be a Work resource because the shovel actually does "work" in the project. And when you make the Shovel resource a Work resource, you can view and analyze resource availability for this resource, which you CANNOT do if you make the Shovel a Material resource. Hope this helps.
Your mistake is assuming that the Shovel resource is a Material resource. The Shovel resource needs to be a Work resource because the shovel actually does "work" in the project. And when you make the Shovel resource a Work resource, you can view and analyze resource availability for this resource, which you CANNOT do if you make the Shovel a Material resource. Hope this helps.