Forum Discussion

Marcos_Berenguel's avatar
Marcos_Berenguel
Copper Contributor
Jan 05, 2025
Solved

Assign Resources with Units = 50%

There is a resource created on "Resource Sheet" as detailed below:
Resource Name: Resource 1
Type: Work
Max. Units: 100%
Base Calendar: Standard

Just double click on this resource to get "Resource Information" dialog box and insert the values below on "Resource Availability" field:
Available From        Available To        Units
NA                          02/01/2025         100%
03/01/2025            06/01/2025            50%
07/01/2025                  NA                 100%

There is a task created on "Gantt Chart" without resource assigned as detailed below (this is the first task and there is no other custom settings):
Task Name: Task 1
Task Mode: Auto Scheduled
Duration: 1 day
Type: Fixed Units
Effort-Driven: Yes
Start: Fri 03/01/25
Fisnis: Fri 03/01/25

After the assignement of "Resource 1" to this same task the "Gantt Chart" display:
Task Name: Task 1
Task Mode: Auto Scheduled
Duration: 1 day
Work: 4 hrs
Type: Fixed Units
Effort-Driven: Yes
Start: Fri 03/01/25
Fisnis: Fri 03/01/25
Resource Names: Resource 1[50%]

The Project Start Date is Fri 03/01/25 (date format used is DD/MM/YYYY).

Desired Outcome: the "Task 1" with Duration: 1 day (i.e. 8 hours) should finish on "06/01/2025" due to "Resource 1" has "Resource Availability" as detailed above (Available From: 03/01/2025 Available To: 06/01/2025 Units: 50%).

If anyone knows what I might be doing wrong, I’d greatly appreciate the help.

  • Marcos,

    What you are doing "wrong" is assuming that duration equates to work. It does not. When you assign the resource to the task, that resource is only available for 4 hours on 3/1/25 so that's all he/she works.

    If your intent is to have the work content at 8 hours, set the Work field value before assigning the resource. Then when you assign the resource the task will be spread over 2 days (i.e. 4 hours each day based on that resource's availability) with a start on 3/1/25 and a finish on 6/1/25.

    Hope this helps.

    John

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Marcos,

    What you are doing "wrong" is assuming that duration equates to work. It does not. When you assign the resource to the task, that resource is only available for 4 hours on 3/1/25 so that's all he/she works.

    If your intent is to have the work content at 8 hours, set the Work field value before assigning the resource. Then when you assign the resource the task will be spread over 2 days (i.e. 4 hours each day based on that resource's availability) with a start on 3/1/25 and a finish on 6/1/25.

    Hope this helps.

    John

    • Marcos_Berenguel's avatar
      Marcos_Berenguel
      Copper Contributor

      John,
      I followed your step-by-step and it was solved.
      Thank you very much.
      Marcos

      • John-project's avatar
        John-project
        Silver Contributor

        Marcos,

        You;re welcome and thanks for the feedback.

        John