Forum Discussion
Marcos_Berenguel
Jan 05, 2025Copper Contributor
Assign Resources with Units = 50%
There is a resource created on "Resource Sheet" as detailed below: Resource Name: Resource 1 Type: Work Max. Units: 100% Base Calendar: Standard Just double click on this resource to get "Resour...
- Jan 06, 2025
Marcos,
What you are doing "wrong" is assuming that duration equates to work. It does not. When you assign the resource to the task, that resource is only available for 4 hours on 3/1/25 so that's all he/she works.
If your intent is to have the work content at 8 hours, set the Work field value before assigning the resource. Then when you assign the resource the task will be spread over 2 days (i.e. 4 hours each day based on that resource's availability) with a start on 3/1/25 and a finish on 6/1/25.
Hope this helps.
John
Marcos_Berenguel
Jan 07, 2025Copper Contributor
John,
I followed your step-by-step and it was solved.
Thank you very much.
Marcos
John-project
Jan 07, 2025Silver Contributor
Marcos,
You;re welcome and thanks for the feedback.
John