"As late as necessary contraint"
Hello, I have a big project with most tasks being dependent on a "Construction start" milestone. That whole structure is set up and works nicely. Now I have to add some land clearing work as "second...
Ignacio_Martin
Jun 27, 2025Iron Contributor
Hi Markurz
You can try the Start to Finish (SF) link between Id=8 Construction start (Predecessor) and Id= 10 land clearing (Successor).
You can even give the link lag time by entering a negative duration in the link Lag field.
Example:
Predecessor of task Id=10 (land clearing): 8SF-4 d
I hope this helps
Ignacio