constraints
1 Topic"As late as necessary contraint"
Hello, I have a big project with most tasks being dependent on a "Construction start" milestone. That whole structure is set up and works nicely. Now I have to add some land clearing work as "secondary tasks", they can be executed before the "Construction start"-milestone but they must not delay the main tasks. The land clearing work can only be performed in winter because of bird protection periods, I have set that up with a ressource. The result looks something like this: My problem is I want the land clearing work to be performed as late a necessary, not years in advance at the project start, but without delaying the end date. If I set the task to be scheduled "as late as possible" it moves everything else back and it overloads my resource aswell: Is there a way to fix this without setting manual Dates? The start dates are not yet fixed and I want as few fixed dates as possible so I dont have to manually adapt everything incase there's a change.109Views0likes3Comments