Forum Discussion

JLewisSafeFlight's avatar
JLewisSafeFlight
Copper Contributor
Sep 01, 2023

Adding Specific Criteria to Established Baseline

I am working on a highly complex and visible schedule and I continue to come across features that I would like to incorporate that require updates to be made to the baseline. I do not want to lose my current baseline of effort but I want to add a cost metric to that existing baseline. Is there a way to just add a cost to an existing baseline without overwriting any other data contained in that baseline?

 

Thank you!

  • John-project's avatar
    John-project
    Silver Contributor

    JLewisSafeFlight

    You can create a custom Cost field but it won't be timescaled like other baseline fields.

     

    What exactly do you want to do with this new metric?

     

    John

    • JLewisSafeFlight's avatar
      JLewisSafeFlight
      Copper Contributor
      I am trying to set up CPI and SPI metrics as part of my overall project status report
      • John-project's avatar
        John-project
        Silver Contributor
        JLewisSafeFlight,
        Does the existing Cost field not allow you to do that? If not, why not?
        John

Resources