Adding Specific Criteria to Established Baseline
I am working on a highly complex and visible schedule and I continue to come across features that I would like to incorporate that require updates to be made to the baseline. I do not want to lose my...
John-project
Sep 01, 2023Silver Contributor
You can create a custom Cost field but it won't be timescaled like other baseline fields.
What exactly do you want to do with this new metric?
John
- JLewisSafeFlightSep 01, 2023Copper ContributorI am trying to set up CPI and SPI metrics as part of my overall project status report
- John-projectSep 01, 2023Silver ContributorJLewisSafeFlight,
Does the existing Cost field not allow you to do that? If not, why not?
John