Forum Discussion

Matthew Russell's avatar
Matthew Russell
Copper Contributor
Nov 14, 2022
Solved

Add successor column to Project online view

Hi

I cant seem to add in the project successor column into my tasks summary view

It doesn't appear in the list of options to add so ive tried adding a custom field to pull the information from the project plan using the formula [Successors]

That creates a column but doesn't pull the info

Any ideas how I can get the column into view?

Thanks

Matt 

3 Replies

  • Hello Matthew Russell ,

    Only the Predecessors column is there to add by default. If you have created a new task level formula field for the Successors in the Enterprise Custom Fields admin area in PWA Settings, you will need to republish those projects for the new field to be populated with the values.

    Paul

    • Matthew Russell's avatar
      Matthew Russell
      Copper Contributor
      Thanks Paul
      That worked. Is there any way to add successor into the online view as an editable field or is the formula field the best option?
      Matt

Resources