Forum Discussion
Matthew Russell
Nov 14, 2022Tin Contributor
Add successor column to Project online view
Hi I cant seem to add in the project successor column into my tasks summary view It doesn't appear in the list of options to add so ive tried adding a custom field to pull the information from the ...
- Nov 14, 2022
Only the read-only calculated field option for the successor column in PWA Matthew Russell
Paul_Mather
Nov 14, 2022MVP
Hello Matthew Russell ,
Only the Predecessors column is there to add by default. If you have created a new task level formula field for the Successors in the Enterprise Custom Fields admin area in PWA Settings, you will need to republish those projects for the new field to be populated with the values.
Paul
Matthew Russell
Nov 14, 2022Tin Contributor
Thanks Paul
That worked. Is there any way to add successor into the online view as an editable field or is the formula field the best option?
Matt
That worked. Is there any way to add successor into the online view as an editable field or is the formula field the best option?
Matt
- Paul_MatherNov 14, 2022MVP
Only the read-only calculated field option for the successor column in PWA Matthew Russell