Forum Discussion

Smeac81's avatar
Smeac81
Copper Contributor
Jun 17, 2024
Solved

% Complete and % Work Complete do not update with Actual Start change.

Changing the date in Actual Start does not update the values in % Complete and % Work Complete columns, they stay at 0.  If the Actual Finish date has any date at all, the percentages go to 100%.

 

Is Project supposed to be automatically calculating those % complete columns or am I missing steps?

 

Windows 11

Project Online Desktop Client v2405

  • Smeac81,
    Simply entering an actual start date will not show a value in either Percent Complete field. You need to also enter a value in the Actual Duration or Actual Work field. However, entering a value in the Actual Duration or Actual Work field first, will cause Project to calculate a value for the Percent Complete fields.

    John

3 Replies

  • John-project's avatar
    John-project
    Silver Contributor
    Smeac81,
    Simply entering an actual start date will not show a value in either Percent Complete field. You need to also enter a value in the Actual Duration or Actual Work field. However, entering a value in the Actual Duration or Actual Work field first, will cause Project to calculate a value for the Percent Complete fields.

    John
    • Smeac81's avatar
      Smeac81
      Copper Contributor

      John-project   I added the Actual Work column, entered in a value and the % Complete columns updated accordingly - that was the step I was missing.

       

      Thanks for the info, much appreciated.

      • John-project's avatar
        John-project
        Silver Contributor
        Joe,
        You're welcome and thanks for the feedback. If I answered your question, please consider marking my response as the answer.
        John