% Complete and % Work Complete do not update with Actual Start change.

Changing the date in Actual Start does not update the values in % Complete and % Work Complete columns, they stay at 0.  If the Actual Finish date has any date at all, the percentages go to 100%.   ...
  • John-project's avatar
    Jun 17, 2024
    Smeac81,
    Simply entering an actual start date will not show a value in either Percent Complete field. You need to also enter a value in the Actual Duration or Actual Work field. However, entering a value in the Actual Duration or Actual Work field first, will cause Project to calculate a value for the Percent Complete fields.

    John