Rolling Out: Copy Planner tasks
Hi, Ability to copy Planner tasks as announced during Ignite started rolling out. I can see it in our tenant.
Lorraine Stevens
Nov 14, 2017Copper Contributor
Hi Santhoush! Thanks for posting this. I did notice that it only allows you to copy a task within the same plan. I tried to go to 'My Tasks', go to Plan View, copy a task and then try to drag and drop it into a different plan (bucket). This does not work. Do you know if there is a workaround to this, to copy a task from one plan to another?
- SanthoshB1Nov 15, 2017Bronze Contributor
Hi, MSFT has not offered this feature yet. It is now possible only to copy tasks within a plan. You can rely on Graph API for this if you can make it or go for third party apps which offers this feature.