Forum Discussion
JohanG1973
Sep 21, 2020Copper Contributor
Teams - Different Channels - Task Planner - assignment of taks to different people isn't possible
Hi, I've made a Team with 11 channels. I'v made with planner different tasks and subtasks. I've copied these tasks to the other 10 channels. When I assign a task to a team member for channel 1. T...
- Sep 21, 2020
JohanG1973 - when you hover over any task card and click the more menu (...) you'll see the option to copy, you can then select what you'd like to copy, i.e., description, due date, assignee, etc. and then choose where you'd like to copy the task to.
Sep 21, 2020
Hi JohanG1973 - if you're pinning the same Planner across all 11 channels, then that is the expected behavior. Planner doesn't recognize what channel it's pinned on, it's the same Planner/buckets/tasks no matter where you view it from. You could create a bucket for each channel or you could create a Planner for each channel.
Hope that helps!
JohanG1973
Sep 21, 2020Copper Contributor
Kelly_Edinger Thanks Kelly for the quick response.
I understand that i can create for each channel a different planner. But the tasks are al the same for the different channels only different executors of the tasks. I just want to copy the tasks and assign different executors if that's possible so i don't have to repeat typing the same tasks...
Thanks...
- Sep 21, 2020
JohanG1973 - when you hover over any task card and click the more menu (...) you'll see the option to copy, you can then select what you'd like to copy, i.e., description, due date, assignee, etc. and then choose where you'd like to copy the task to.