In Gantt timeline, change date cell color when status changes for that date range
I have a Gantt chart project plan with fields Start Date, End Date & Status (To Do, In Progress & Done).
Whenever i change the status, i need the colour of the selected date range cells to be changed in the timeline section.
For example, as shown in the attachent, when i change the status for the start date - end date range 25-Jun-21 - 06-Jul-21, the corresponding date cells in the timeline portion should change to a different color.
Hope someone can help me out.
6 Replies
Please attach a small sample workbook, or make it available through OneDrive, Google Drive, Dropbox or similar.
- arunnairsCopper ContributorAs of now, depending on the start date and end date selection, the date cells in timeline portion gets filled with a color. (Currently violet is given)
The status column has 3 values namely To Do, In Progress and Done.
Whenever I change the status, i need the color of the timeline cells corresponding to the start date & end date should change.
Colors can be chosen as follows:
To Do - Red
In Progress - Yellow
Done - Green.
Hope this makes sense.