Forum Discussion
E_Buck2010
Jun 02, 2023Copper Contributor
How do I display duration data in a Stacked Bar Chart using dates?
I want to display the duration of my projects in a chart using the dates (quarters). I tried using the date data but the chart does not display the way I want. I was able to display the data using the actual duration data but that doesn't map to the quarters.
Can you please let me know how I need to setup the data to have the dates as the hortizonal axis?
Thanks in advance!
This is the data the chart is based on.
Resources | Project Name | Feasability | Initiation | Programming & SD Phase | Authorization | DD & CD Phase | Construction | Approval |
Mary Jones | ||||||||
Jackson Library | 775 | 238 | 20 | 209 | 627 | 20 | ||
Macon GA Court House | 772 | 53 | 20 | 93 | 837 | 20 | ||
LA Center | 257 | 439 | 20 | 339 | 997 | 20 | ||
NYC 5th Avenue | 70 | 175 | 387 | 20 | 369 | 625 | 20 | |
Keller Museum | 70 | 175 | 387 | 20 | 369 | 625 | 20 | |
Kevin DeMichel | ||||||||
CUBs Stadium | 72 | 213 | 20 | 165 | 420 | 20 | ||
Dan Mitchell | ||||||||
Newark DE Library | 356 | 303 | 20 | 256 | 644 | 20 | ||
John Daily | ||||||||
Sears Tower | 100 | 100 | 100 | 100 | 100 | 100 | 100 |
This is the RAW data:
Project | Resource | Activity Name | Start | Finish | Original Duration |
Jackson Library | Kevin DeMichel | Feasability | 27-Nov-17 | 20-Aug-18 | 0 |
Initiation | 17-Aug-18 | 20-Nov-20 | 775 | ||
Programming & SD Phase | 20-Nov-20 | 19-Dec-20 | 238 | ||
Authorization | 19-Dec-20 | 23-Sep-22 | 20 | ||
DD & CD Phase | 7-Oct-22 | 13-Oct-25 | 209 | ||
Approval | 1-May-23 | 26-May-23 | 627 | ||
Construction | 30-May-23 | 30-May-23 | 20 | ||
CUBs Stadium | Christina Marzocca | Feasability | 27-Nov-17 | 20-Aug-18 | |
Initiation | 15-Aug-18 | 29-Jun-20 | |||
Programming & SD Phase | 29-Jun-20 | 27-Jul-20 | |||
Authorization | 27-Jul-20 | 23-May-22 | |||
DD & CD Phase | 9-Feb-22 | 4-Jun-25 | |||
Approval | 1-May-23 | 26-May-23 | |||
Construction | 30-May-23 | 30-May-23 | |||
Newark DE Library | Dan Mitchell | Feasability | 27-Apr-20 | 12-Aug-24 | |
Initiation | 27-Apr-20 | 5-Jul-21 | |||
Programming & SD Phase | 5-Jul-21 | 23-May-22 | |||
Authorization | 23-May-22 | 17-Jun-22 | |||
DD & CD Phase | 17-Jun-22 | 26-May-23 | |||
Approval | 29-May-23 | 26-Jun-23 | |||
Construction | 31-May-23 | 12-Aug-24 |
Use the start date as first series, but make its bars transparent. Simplified example:
Workbook attached
Use the start date as first series, but make its bars transparent. Simplified example:
Workbook attached
- jlackmanCopper Contributor
slick solution!
- E_Buck2010Copper Contributor
HansVogelaar Thank you! That worked.
- E_Buck2010Copper ContributorI don't see an option to just upload the Excel document.