Forum Discussion

Crispin2410's avatar
Crispin2410
Copper Contributor
Nov 05, 2021
Solved

Formula Assistance Crispin

I need assistance with multiple cells/formulas.

 

1) In the attached example C4 is the date required for the contractor to submit the CDRL. D4 is the actual date the CDRL was received.

 

     a) I would like C4 to turn yellow when it is 10 days from being due. Then turn red if it exceeds the due date. Once a date in D4 is entered regardless of whether its late or not, cell C4 turns green. 

     b) Once a date is entered in D4, cell E4 changes from "Pending" to "Completed"

 

2) F4 is a 15 day countdown from when a date is entered in D4. At 5 days it turns yellow. If the countdown exceeds is turns from + to - number and changes from yellow to red. Once a date in G4 is entered then the countdown changes from red to green, and the countdown stops at the last number before a date was entered in g4.

 

 Thanks!


C

5 Replies