Excel question > calculate workdays

Hi,

I have task that need to end at 31-Mar.

the working days to finish this task is 7 days.

ho do I calculate what should be the start date in order to finish at the 31-Mar when I have only 5 working days a week?

 

Thx

  • Orgo123 

    Let's say the end date 31-Mar is in E2 and the number of working days in F2.

    The formula for the start date is

     

    =WORKDAY(WORKDAY(E2+1,-1),1-F2)