Forum Discussion
Excel Project Gantt Chart: Adding Milestone Diamond
- Mar 09, 2023
I have received the workbook. The problem was not in the character, but in the formula.
The formula in J6 should be
=IF(J$4=$E6-WEEKDAY($E6,13)+7,"u","")
with the font set to Wingdings. Fill to the right and down. See the attached version.
And I have tried it on multiple computers.
I have attached a sample workbook. This is what I see in it:
What do you see when you open it?
- DavinAinebyonaMar 09, 2023Copper Contributor
The same thing. I don't understand why it isn't working for just the Gantt chart
- HansVogelaarMar 09, 2023MVP
I have received the workbook. The problem was not in the character, but in the formula.
The formula in J6 should be
=IF(J$4=$E6-WEEKDAY($E6,13)+7,"u","")
with the font set to Wingdings. Fill to the right and down. See the attached version.
- annalwFeb 23, 2024Copper Contributor
I am also struggling with getting milestones on my chart and I can't seem to figure out what isn't working. Would you be able to help me ? HansVogelaar
- HansVogelaarMar 09, 2023MVP
Could you attach a small sample workbook demonstrating the problem (without sensitive data), or if that is not possible, make it available through OneDrive, Google Drive, Dropbox or similar? Alternatively, you can attach it to a private message to me. Thanks in advance.