Excel formula
For gantt type chart I have a start date - in column I have =TODAY()-F9 the start date. I want to show days completed - my issue that if todays date is past the end date, it continues to show todays date to the start date. I want it to show it to show the days completed but no more than the number of days within the range of start to end date? So for cell K9 I want it reflect 21 days. Days completed should never exceed work days. Help!!
- Chris-RessConsultingBrass Contributor
Hello sharrinwest,
Please see the attached worksheet. Thanks!
Let me know if this isn't what you were looking for.