Calculate days remaining in a task based on start date and percentage done.
Hi, I've searched for a solution for this but I'm struggling, possibly in part due to brain fog!
I'm part of a big migration project, and I have a formula that works out how far along the project is (C100) and a start date of 6th Feb 2023.
The percentage completed figure in C100 fluctuates based on new data coming in and the complexity of the work (it just jumped from 87% to 61%!), so I know it's not going to be accurate, but can someone help with with a formula that works out the number of days remaining until the task is completed based on the start date and the percentage done?
Thank you in advance.
Let's say the start date (6th Feb 2023) is in D100.
The end date is returned by
=D100+100%/C100*(TODAY()-D100)
Format the cell with the formula as a date.