Forum Discussion
Allocating manhours to a month-to-month from a construction schedule
Good day,
I need assistance with separating manhours by month from a construction schedule. The schedule includes a start date, a finish date, and the total man-hours for the duration of each activity. I want to divide these manhours among the specified months for each activity so that I can create a Bell Curve for manhours for each month of the year.
While this can be accomplished using the Excel Macros Developer program, I am unsure how to perform the extraction and separation correctly. Could someone please help me with this process?
Thank you!
PS: The full version has over 2,000 activities
| Start | Finish | Manhours |
| 22 February 2026 | 17 May 2026 | 1871 |
| 11 March 2026 | 23 May 2026 | 250 |
| 17 December 2026 | 25 February 2027 | 5988 |
| 23 May 2026 | 08 August 2026 | 4790 |
| 08 August 2026 | 25 August 2026 | 250 |
| 25 August 2026 | 30 September 2026 | 1248 |
| 30 September 2026 | 10 October 2026 | 524 |
| 10 October 2026 | 14 November 2026 | 2994 |
| 21 July 2026 | 30 September 2026 | 5988 |
5 Replies
- PeterBartholomew1Silver Contributor
This is a 365 formula that works on a 7 day week basis.
Worksheet formula = REDUCE(0,Activity,DistributeHoursλ(Manhours, Start, Finish)) DistributeHoursλ = LAMBDA(_hours,_start,_finish, LAMBDA(acc, seq, LET( hours, INDEX(_hours, seq), start, INDEX(_start, seq), finish, INDEX(_finish, seq), timeline, 1 + EOMONTH(DATE(2026, 1, 0), SEQUENCE(16, , 0)), open, SORT(VSTACK(start, timeline)), close, SORT(VSTACK(finish, timeline)), days, DROP(close - open, 1), acc + hours * days / SUM(days) ) ))- pelserbenCopper ContributorSorry Peter, see my response to Hans. Thanks,
- PeterBartholomew1Silver Contributor
Don't worry, the problem has a sufficiently generic interest to make it worth solving as a challenge. I have introduced NETWORKDAYS but I could easily have made an error accounting for the various inclusive or exclusive date intervals. Using NETWORKDAYS with weekend = 16
DistributeWkHrsλ = LAMBDA(_hours,_start,_finish, LAMBDA(acc, seq, LET( hours, INDEX(_hours, seq), start, INDEX(_start, seq), finish, 1 + INDEX(_finish, seq), timeline, 1 + EOMONTH(DATE(2026, 1, 0), SEQUENCE(16, , 0)), open, SORT(VSTACK(start, timeline)), close, SORT(VSTACK(finish, timeline)), days, DROP( NETWORKDAYS.INTL(open, close, 16) - NETWORKDAYS.INTL(close, close, 16), 1), hrs, hours * days / SUM(days), acc + hrs ) ))
How should the hours be allocated to the months? Based on the number of calendar days in each month? Or on the number of working (non-weekend) days in each month? Do we have to take public holidays into account?
- pelserbenCopper Contributor
HansVogelaar Hans, the schedule is based on 6 days a week, only Fridays are excluded, as this project is in the Middle East. The process is to extract the months-to-month between the start and finished dates and then allocate the manhours prorate to each month based on the months within each line activity and the respective days in the relevant months. I was informed that one must use Developer with Macros in Excel, and then insert a formula and the system will automatically do the extraction and manhour allocation. But I don't have the knowledge to do the formula/s.