Forum Discussion
Adding Sat/Sun back to Gantt Chart Calendar
- May 04, 2023
normabeez Sorry. Forgot about the fact that the file had been posted already. Took another look at it and made some changes.
The end date is now based on the start date plus the number of days it takes to complete the task. Then I changed the formula in the grid to return zero is the day starts with "S". That will prevent the milestone icons to show. Lastly, I greyed out all Saturdays and Sundays in the grid. Is that what you had in mind?
See attached.
Appreciate your honesty and I get it. However it was the most convenient option at the moment. I had attached the file in my original post.
normabeez Sorry. Forgot about the fact that the file had been posted already. Took another look at it and made some changes.
The end date is now based on the start date plus the number of days it takes to complete the task. Then I changed the formula in the grid to return zero is the day starts with "S". That will prevent the milestone icons to show. Lastly, I greyed out all Saturdays and Sundays in the grid. Is that what you had in mind?
See attached.
- normabeezMay 08, 2023Brass ContributorRiny_van_Eekelen Apologies for the delayed response, I was OOO the last few days. Thank you so very much for your assistance! THIS IS PERFECT! Thank you again for your time, it is so very much appreciated!