4 TopicsTwo resources changing their base calendar simultaneously
Hi, I'm using Project Professional 2019. I've created some base calendar for all the projects that I have. I have two resources that when I change the base calendar of one of them, the other one is changed too, in a way that I can't choose differents base calendar for this two resource. I don't know if this is a issue or not, maybe someone experienced this and knows what is wrong... Thanks!Solved2.2KViews0likes9CommentsExporting Project - Resource Usage table with phased time data to excel
Hi Experts, Is there a way to export tasks to excel while retaining the phased time cost data? In an ideal world I would like to export this info and for it to look like this in excel: Export wizard is not doing the trick. Good old copy paste is copying the Resource list, but not the time phase. Any ideas?2.3KViews0likes7CommentsWhat's the best way to graphically view resource utilisation in Project?
Long time P6 user, looking for something similar to this in MSP... A list of all my resources, against their utilisation in graphical (not tablature) form I've tried Resource Graph, but that seems like you have to scroll around to see the resources - i cant select more than one resource to see cumulative Any suggestions appreciated DavidSolved3.4KViews0likes5CommentsResource with elapsed days
Hello team . I have a uneasiness. If a 3.66 hour activity (09:00 – 13:00) with a 20-minute break. It has resources (People) that take the break and others don't (equipment), working in full for the total 4 hours of the activity. How can I configure this resource (equipment) to work the full 4 hours? Without affecting others or becoming undercharged.Solved1.2KViews0likes3Comments