Project - Resource Leveling
Hello, I've created a Resource ("INDRSI") with 4 units available. I've created two tasks: AAA: 60 work days, prio 900, 1 unit BBB: 600 work days, prio 500, 4 units With Resource->Level execution, Leveling order "Priority, Standard", I see that Project firstly plans task AAA and afterwards task BBB. It means that in the first 60 days, only 1 unit is used. In order to fully book my team, I'm wondering which leveling options / other task or resource configurations I should choose in order to Level in a way that: - both task AAA and task BBB start together - In the first 60 days, task BBB would use 3 units only (because task AAA already utilizes 1 unit). - After 60 days, task AAA is finished, so task BBB would be covered with 4 units. Thanks a lot for your support! Claudio564Views0likes0Comments