Project - Resource Leveling
Hello,
I've created a Resource ("INDRSI") with 4 units available.
I've created two tasks:
- AAA: 60 work days, prio 900, 1 unit
- BBB: 600 work days, prio 500, 4 units
With Resource->Level execution, Leveling order "Priority, Standard", I see that Project firstly plans task AAA and afterwards task BBB.
It means that in the first 60 days, only 1 unit is used.
In order to fully book my team, I'm wondering which leveling options / other task or resource configurations I should choose in order to Level in a way that:
- both task AAA and task BBB start together
- In the first 60 days, task BBB would use 3 units only (because task AAA already utilizes 1 unit).
- After 60 days, task AAA is finished, so task BBB would be covered with 4 units.
Thanks a lot for your support!
Claudio