Tracking unit progress on ms project
I am trying to figure out how to get MSP to measure my work correctly. Example: I have 10 days to install 10,000 feet of cable. On day one I install 2500 feet and put my progress in as 25%. The problem is my task bar and days show 2.5 days have been used which is incorrect. I want to see my actual percent complete based on the actual amount of time (days) I use. It can work the other way. I can take 3 days to lay 1000 ft. I don't want my task bar to say I've only used one day when I actually used 3 days. Please help. ShawmanSolved1.2KViews0likes3Comments