May 21 2024 01:57 PM
How do I account for working hours changing after a project has started? If I create a project with a custom calendar and have 6 days a week 10 hours each day and then this changes to 5 days and 8 hours a week....or the reverse of this.
May 21 2024 07:15 PM
There are a few different ways to handle your scenario. The best method to use depends on the status of your plan. For example, were some tasks complete based on the extended work week, while some tasks are in progress and need a work week shift midway through and perhaps yet other tasks that haven't started but will need to do so under a normal 8-5 work week?
Here are a few of the methods you might consider.
1. If your plan is mostly done with the extended work week and only a limited number of tasks will be on the new work week, you may consider adding exceptions to your custom calendar to basically timescale the new work week
2. For in-progress tasks that need to switch, break the task into two parts with the first part of the task on the extended work week and the new part on the new work week
3. Tasks that have not yet started can use the 8-5 work week calendar (Standard) as their Task Calendar.
Those are a few ideas, maybe others will jump in with their thoughts.
John
May 22 2024 05:53 AM
John, I like all three of your suggestions.
The hours we estimate originally and use to create our plan/schedule can (and often do) change mid projects. This is either a result of us being ahead or behind on a task or the customers schedule changing which could cause our schedule to change.
May 22 2024 08:43 AM