Forum Discussion

JLGregoryIBM's avatar
JLGregoryIBM
Copper Contributor
Jan 26, 2022
Solved

Why do projects disappear from the Project Center when added to a Master Schedule?

We have a requirement to perform reporting both at the program / portfolio and individual project levels. We wanted to use the Project Center (PWA) for portfolio reports while also pulling those proj...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Jan 27, 2022
    JL Gregory --

    What you are describing is a new feature that was added to the Project Center page in PWA some years ago. To my regret, I believe the new feature has caused people a bit too much confusion and heartache. By default, the Project Center is now configured to display only single projects and master projects, but NOT to display subprojects in a master project. To display the subprojects of a master project in the Project Center page, first expand the Projects ribbon. Then all you need to do is to click the Subprojects checkbox in the Show/Hide section of the Project ribbon. Voila! The subprojects will magically appear. Hope this helps.

Resources