Hi all,
We are in the process of configuring Project Online for my company and we would like to populate the Resource Pool with Azure AD groups, and then pull certain attributes for each user (e.g. location, phone number, etc.) We came across this script, but since it's a few years old I was wondering if anybody has come across (or uses) something else that makes the syncing possible.
Thanks in advance!
Cyn
Jan 19 2020 11:46 PM
Hello @Cyndera ,
I published that script, I'm not aware of any other scripts or apps that do that but hopefully that script will still give you a good starting point.
Paul
Jan 21 2020 05:56 AM
Hi @Paul Mather, thank you so much for your reply! Really appreciate it :)