Mar 02 2023 11:54 PM
hi everyone,
if for a task I have 100 hours available but for this project I can dedicate only 20% of the resource how do I get the correct task duration?
Mar 03 2023 05:26 AM
Mar 03 2023 06:04 AM
thanks for the quick response!
what do you mean by work value? i don't have that field on task information 😞
Mar 03 2023 09:01 AM - edited Mar 04 2023 07:17 AM
Andrea -
It sounds like you are using the Microsoft Project desktop application. Select the task in question. Apply the Gantt Chart view, then right-click anywhere in the white part of the Gantt Chart screen on the right side of the view and then click the Show Split item on the shortcut menu. This will apply a view known as the Task Entry view, and you will see the Task Form view in the bottom pane. In the bottom pane, you can select the name of the resource, enter a Units value, and enter a Work value as well. Hope this helps.