I have a "Task A" planned for 2 weeks, 80 hours workload, one person appointed with 100% availibility.
Today this task is complete with only 40 hours spent (so, another 40 are now my reserve).
There is a command "Mark as complete" on the page "Tasks" of Project online, so the person used this command, as result all other 40 unspent hours were automatically put in a schedule of the person as already spent shours for the future schedule.
What I want is task to become 100% complete, but fact stay as fact with planned workload reduced to gain 100% completion status.
This way I loose actual workload in the project data, because system increase it to initially planned workload.
Is there any option to keep fack as is and change plan to have 100% completion, or should I edit project hours manually in the desktop application to decrease planned hours to have task 100% complete?