Forum Discussion

NKumar2010's avatar
NKumar2010
Brass Contributor
May 23, 2022

Show Dependency without Changing Timelines

Hi,    I have three tasks, let's call it Task A, B and C.    Task A is predecessor (FS relation) of Task C. So task C's start date is dictated by Task A finish date.   Task B is not a predecesso...
  • Dale_HowardMVP's avatar
    May 23, 2022
    NKumar2010 --

    No, what you want to do is not possible. I would recommend you link Task A and Task C with an FS dependency, and then link Task B and Task C with an FS dependency as well. Hope this helps.

Resources