See a resource's capacity

Brass Contributor

I am using Project Accelerator, and the PowerBI reports.  I do not see an easy way to see a resource's available capacity.  I can see what they are assigned for tasks but I cannot see the that against their current capacity. 

 

Is there any way to see a resource's total capacity?

3 Replies
psawyer,
I have no experience with Project Accelerator or PowerB1 but there are a couple of fields in Project that show a resource's capacity: Unit Availability and Work Availability. Maybe you can leverage off those.

Just a thought.
John

@John-project 

 

I found this blog post, and was able to implement this.  It was a lot more challenging than it needed to be.

 

Working with the ExpandCalendar Function in Power BI Desktop (Microsoft Dataverse / Dynamics 365) (c...

psawyer,
I'm glad you found something to help. Since you answered your own question, you can mark your last past as the answer.
John