Forum Discussion
Robdonty1395
Jun 01, 2023Copper Contributor
Save a Project Centre View as a Site Page
How do I save a Project Centre view as a site page? I am an administrator and want to have quick links to take others in my organisation direct to the active and archived projects, as shown here: ...
- Jun 02, 2023
Hello Robdonty1395 ,
Unfortunately this is not possible as there is no support for URL query strings in the Project Center URLs. The Project Center views will take the user to the last view they used.
Paul
Paul_Mather
Jun 06, 2023MVP
Hello Robdonty1395 ,
Can you review that other instance, maybe they have custom code, JavaScript etc., on the page that selects the correct project center view if they are using the out of the box project center grids.
Paul
Robdonty1395
Jun 07, 2023Copper Contributor
Hi Paul, I do not have administrator rights on the other teams PWA site and am a newby to this myself as well. The person who administers the other teams PWA is not the person who set it up, so they are not fully versed either. Is there an easy way that I can tell the other administrator to look for this information? I would not know where to start!
- Paul_MatherJun 08, 2023MVP
Hello Robdonty1395 ,
Edit the page and see what webparts are added / check for any custom code etc.
Paul