Resources Calender and availibility
Good morning, Pls assist .. I have a 2 calenders on this project. 1. Fabrication 2. Installation. (I've allocated it accordingly to my tasks.) For this project (SAPPI) my Resources for : 1.'Fabri...
- Sep 27, 2024
Hi Jeanine.
The maximum capacity shown in the resource sheet refers to the current day, so if that day is outside the resource's availability range, it will show 0%.
You can check the maximum capacity on any day of the resource's availability range by entering a date within the range in Project > Properties > Project Information > Current Date.
I hope I have helped you.Ignacio Martin
JeanineB007
Sep 27, 2024Copper Contributor
I need to get the 'end date' of this task from 19/11 to be not later than 03/11, without affecting the fixed welding work 298.2 hr??? How do I fit it in to complete not later than 03/11. Team 1: 1-welder 100% + i) add another welder (200%) = should cut completion date to half/ or use team 2 (if to balance the 298.2 - the required 226 hrs = 72.2 hrs over) Thus add 32% from team 2 needed to bring date to 03/11....correct? Why then does it change the duration to '0' and the start date & end date to predecessor (AC inspection) end date.... should it not level the date from the 19/11/2024 (Team 1 - 100%) to 03/11/2024 (Team 2 - 32%)....please assist
- Ignacio_MartinSep 27, 2024Iron Contributor
Jeanine, in order to help you with your second question, it would be desirable for you to show a screenshot of the tasks table with the tasks to which you refer with their data.
RegardsIgnacio Martin