Resources Calender and availibility

Good morning, Pls assist .. I have a 2 calenders on this project. 1. Fabrication  2. Installation. (I've allocated it accordingly to my tasks.) For this project (SAPPI) my Resources for : 1.'Fabri...
  • Ignacio_Martin's avatar
    Sep 27, 2024

    JeanineB007 

    Hi Jeanine.

    The maximum capacity shown in the resource sheet refers to the current day, so if that day is outside the resource's availability range, it will show 0%.
    You can check the maximum capacity on any day of the resource's availability range by entering a date within the range in Project > Properties > Project Information > Current Date.
    I hope I have helped you.

    Ignacio Martin